Scope of supply | Name of projects | Year | Client | Location |
No 1 Thermophysical Deaerator Q = 446.5T/h |
PT Pertamina Kilang Refinery Unit | ’24 | REKA Energi | INDONESIA |
No 1 Thermophysical Deaerator Q = 160 T/h each |
PTTGC EPS EXP. 3 PROJECT | ’22 | GTB | THAILAND |
No 2 Thermophysical Deaerators Q = 217 T/h each – HEI standard |
RSFFB PROJECT | ’19 | FORMOSA | PHILIPPINES |
No 1 Thermophysical Deaerator Q = 65 T/h – HEI standard |
PTPPE PROJECT | ’19 | GTB | THAILAND |
No 4 Thermophysical Deaerators Q = 473 T/h each- HEI standard |
MPGC PROJECT | ’17 | FORMOSA | PHILIPPINES |
No 1 Thermophysical Deaerator Q = 581 T/h – HEI standard |
PEDC-3 PROJECT | ’14 | FORMOSA | PHILIPPINES |
No 1 Thermophysical Deaerator Q = 550 T/h – HEI standard |
FCFC-VN3 PROJECT | ’14 | FORMOSA | VIETNAM |
No 1 Thermophysical Deaerator Q = 383.5 T/h – HEI standard |
HA TINH PROJECT | ’13 | FORMOSA | VIETNAM |
No 1 Thermophysical Deaerator Q = 205.8 T/h |
APEC PROJECT | ’13 | FORMOSA | PHILIPPINES |
No 1 Thermophysical Deaerator Q = 15 T/h |
ARKEMA-LYCHEE PROJECT | ’13 | FOSTER WHEELER | MALAYSIA |
No 1 Thermophysical Deaerator Q = 534 T/h |
ROPP PROJECT PT PERTAMINA | ’08 | PT REKAYASA | INDONESIA |
No 1 Thermophysical Deaerator Q = 240 T/h |
SRC REFINERY PROJECT | ’08 | SRC | SINGAPORE |
No 2 Bypass Deaerators Q(D) = 431 T/h each |
Pulau Seraya Power Plant Hydrotest in workshop |
’08 | SIEMENS | SINGAPORE |
No 2 Thermophysical Deaerators Q = 82.5 T/h each |
PTT Utility Co. CUP III Plant | ’08 | CTCI Corporation | THAILAND |
No 1 Thermophysical Deaerators Q = 65 T/h |
PTTPE LDPE Plant Project | ’08 | GTB ENG./TOYO | THAILAND |
No 2 Thermophysical Deaerators Q = 431 T/h each |
PULAU SERAYA SIEMENS POWER PLANT |
’08 | SIEMENS | SINGAPORE |
No 3 Thermophysical Deaerators Q = 220 T/h & 240 T/h |
No 3 Thermophysical Deaerators Q = 220 T/h & 240 T/h |
’07 | CTCI Corporation | THAILAND |
No 2 Thermophysical Deaerators Q = 214 T/h each |
PULAU SERAYA SIEMENS POWER PLANT |
’07 | JEL | SINGAPORE |
No 1 Thermophysical Deaerator Q = 454 T/h HEI standard |
PTT Utility Co.CUP II Plant ( HRSG) | ’06 | GTB ENG. | THAILAND |
No 1 Thermophysical Deaerator Q =62.8 T/h HEI standard |
PTT Utility Co.CUP II Plant( Auxiliary) | ’06 | GTB ENG. | THAILAND |
No 2 Thermophysical Deaerators Q = 696 T/h each |
Petrovietnam Dung Quat Refinery Project |
’06 | TECHNIP /JGC / TR JV | VIETNAM |
No 2 Thermophysical Deaerators Q = 400 T/h each |
Petrovietnam Dung Quat Refinery Project |
’06 | TECHNIP /JGC / TR JV | VIETNAM |
No 2 Thermophysical Deaerators Q = 516 T/h each |
Tangguh LNG Off-Shore Plant | ’05 | JGC KBR JV | INDONESIA |
Thermophysical Deaerator Q = 130 T/h |
TCP New Cogeneration Plant | ’05 | GTB ENG. | THAILAND |
Thermophysical Deaerator Q = 50 T/h |
TPI Project | ’05 | GTB ENG. | THAILAND |